253. In addition to what is required by section 41, the declaration of compliance for an activity referred to in section 252 must include a declaration from an engineer and, where applicable, from an agronomist attesting that the project complies with that section and with the provisions of the Agricultural Operations Regulation (chapter Q-2, r. 26) and the Water Withdrawal and Protection Regulation (chapter Q-2, r. 35.2).
The declarant must send the Minister an attestation from an engineer and, where applicable, from an agronomist that the activity is carried on in accordance with the first paragraph:
(1)  within 60 days from the construction, laying out or modification of composting facility;
(2)  within 12 months after operations at the composting facility begin.
O.C. 871-2020, s. 253.
In force: 2020-12-31
253. In addition to what is required by section 41, the declaration of compliance for an activity referred to in section 252 must include a declaration from an engineer and, where applicable, from an agronomist attesting that the project complies with that section and with the provisions of the Agricultural Operations Regulation (chapter Q-2, r. 26) and the Water Withdrawal and Protection Regulation (chapter Q-2, r. 35.2).
The declarant must send the Minister an attestation from an engineer and, where applicable, from an agronomist that the activity is carried on in accordance with the first paragraph:
(1)  within 60 days from the construction, laying out or modification of composting facility;
(2)  within 12 months after operations at the composting facility begin.
O.C. 871-2020, s. 253.